Construction: Physical construction of the Project is now 70% complete Significant advancement in mine pre-stripping, with first sulphide ore on track to be reached in early November All earthworks now completed, including the water storage reservoir, site drainage and run-of-mine stockpiles Over 15,000 cubic meters of concrete poured (over 65% complete), concluding all major foundation...
December 6, 2024